The Middelgrunden Offshore Wind Farm. A Popular Initiative.

2003

Download : PDF (1,5 MiB)

Resumo :

The idea of the Middelgrunden wind project was born in a group of visionary people in Copenhagen already in 1993. However it took seven years and a lot of work before the first cooperatively owned offshore wind farm became a reality. Today the 40 MW wind farm with twenty modern 2 MW wind turbines developed by the Middelgrunden Wind Turbine Cooperative and Copenhagen Energy Wind is

producing electricity for more than 40,000 households in Copenhagen.

Veja também